Project Description

The site measures 0.053 hectares and comprises two adjoining buildings fronting the busy High Street, with an associated rear service area and garage which was formerly used by H R Owen Bentley car dealership.

151 High Street is a Grade II Listed building and the properties lie within the Monken Hadley Conservation Area.

The site has a relatively complex and protracted planning history, but Planning Permission and Listed Building Consent was granted in October 2020 for 6 residential properties comprising 3no. apartments, 2no. mews cottages, 1no. house and 1no. retail unit.

Building works completed in August 2022.

All Images Copyright: Isabels Visuals

Our Role – Development & Project Management

Managing the project from conception:-

  • Carrying out a viability assessment
  • Reviewing the demand for each type and size of residential accommodation with local agents
  • Selection and appointment of the professional team
  • Preparation and submission of the planning applications
  • Preparation and submission of the planning appeal
  • Preparation of the new planning applications
  • Working up a detailed design
  • Preparing the tender documents
  • Appointing a contractor
  • Managing the building process